Summary of Building Plan
286,150 new housing units across 30 designated growth zones, adding approximately 515,000 residents to San Francisco by 2040. Funded by $22 billion in infrastructure: $5.5B GO bonds, $5.9B developer agreements, $10.6B Mello-Roos districts. Per-unit development cost cut 49% through entitlement reform. Developers build and pay for everything on their own sites.
| ID | Area / District | Current Use | Max Height | Units | Pop. | Notes |
|---|---|---|---|---|---|---|
| 1 | Mission District | Mixed res./comm. | 8-15 stories | 30,000 | 54,000 | 2 BART stations, 24th/16th St corridors |
| 2 | Geary Corridor | Retail strips | 10-15 stories | 35,000 | 63,000 | Miles of 1-story retail on major bus line |
| 3 | 19th Ave Corridor | Comm. + parking | 10-15 stories | 18,000 | 32,400 | GG Park to county line along future BRT |
| 4 | India Basin/Bayview | Indust. + vacant | 10-15 stories | 25,000 | 45,000 | Vacant land + shipyard; lowest cost |
| 5 | East SoMa | Warehouses/tech | 25-35 stories | 25,200 | 45,360 | Remaining warehouse parcels |
| 6 | Mission Bay/Dogpatch | R&D/industrial | 20-30 stories | 15,300 | 27,540 | Dogpatch industrial sites |
| 7 | Mid-Market/Civic Ctr | Civic/lots/retail | 20-30 stories | 12,000 | 21,600 | Best transit in city |
| 8 | Ocean Beach/Gt Hwy | Coastal | 6-8 stories | 10,000 | 18,000 | 3.5 mi Great Hwy frontage |
| 9 | Southern Waterfront | Port/industrial | 20-25 stories | 12,750 | 22,950 | Brownfield + Port jurisdiction |
| 10 | Fisherman's Wharf | Tourist retail | 20-25 stories | 7,800 | 14,040 | Strongest political opposition of any zone |
| 11 | Caltrain Corridor | Railyards/parking | 8-12 stories | 10,000 | 18,000 | Transit-adjacent infill |
| 12 | Outer Mission/Excelsior | Comm. strip | 8-12 stories | 12,000 | 21,600 | Mission St to county line |
| 13 | Lombard St Corridor | Auto/motel/retail | 8-12 stories | 5,000 | 9,000 | Wide 4-lane; Van Ness to Lyon; GG Bridge feeder |
| 14 | Fillmore Corridor | Commercial spine | 8-15 stories | 4,000 | 7,200 | Widest N-S spine between Van Ness & Masonic |
| 15 | Taraval/Sunset Strip | Retail strip | 6-8 stories | 5,000 | 9,000 | L-Taraval Muni Metro; narrow parcels |
| 16 | San Bruno Ave/Portola | Neighborhood comm. | 8-12 stories | 4,000 | 7,200 | Near Bayshore Caltrain; connects to Outer Mission |
| 17 | Treasure Island | Military/vacant | 15-20 stories | 8,000 | 14,400 | City-controlled; master-planned; ferry service |
| 18 | Balboa Park/City College | Parking/institutional | 8-15 stories | 6,000 | 10,800 | BART station; underused parking; City College |
| 19 | Divisadero Corridor | Commercial/arterial | 8-15 stories | 4,500 | 8,100 | Four lanes; strong commercial; Geary node towers |
| 20 | Steiner Street | Residential/comm. | 8-12 stories | 2,000 | 3,600 | Full N-S run Haight to Marina; Geary parcels |
| 21 | Presidio Avenue | Comm./institutional | 6-12 stories | 1,600 | 2,880 | CPMC campus parcels; California to Geary connector |
| 22 | Masonic Avenue | Arterial/comm. | 8-15 stories | 3,500 | 6,300 | Four lanes; wide median; Masonic/Geary tower node |
| 23 | Bay Street | Industrial/warehouse | 8-20 stories | 3,500 | 6,300 | Large-footprint former industrial; deep blocks |
| 24 | Oak/Fell Corridor | Arterial/comm. | 8-15 stories | 4,000 | 7,200 | Highway-width one-way pair; deep parcels |
| 25 | Lake Merced / SF State | Golf/parking/institutional | 10-20 stories | 5,000 | 9,000 | Huge parcels; Stonestown; M-Ocean View Muni |
| 26 | Van Ness Corridor | Commercial/auto row | 15-25 stories | 6,500 | 11,700 | BRT built; 4 lanes; deep parcels; Market to Lombard |
| 27 | Third St / Bayshore South | Industrial | 10-15 stories | 3,500 | 6,300 | T-Third Muni; industrial parcels near Candlestick |
| 28 | Geneva Ave Corridor | Commercial strip | 8-12 stories | 2,500 | 4,500 | Connects Balboa BART to Bayshore Caltrain |
| 29 | Brotherhood Way / J. Serra | Suburban comm. | 8-12 stories | 2,000 | 3,600 | Wide roads; church properties, strip malls |
| 30 | Potrero Hill / 16th St | Industrial/comm. | 10-15 stories | 2,500 | 4,500 | Between Mission & Dogpatch; industrial east slope |
| TOTAL | 286,150 | 515,070 |
| 2030 (Yr 3) | 2033 (Yr 6) | 2037 (Yr 10) | 2040 (Final) | |
|---|---|---|---|---|
| Cumulative Units | 20,188 | 89,686 | 206,730 | 286,150 |
| Cumulative Pop. | 36,338 | 161,435 | 372,114 | 515,070 |
| Annual Recurring Revenue | $210M | $944M | $2,311M | $3,116M |
| Cumulative Total Revenue | $0.8B | $4.0B | $13.2B | $22.7B |
Document Outline
1. Executive Summary
- 286,150 new units, 515,000 new residents, 30 growth zones, 2027-2040
- Per-unit cost cut 49% ($989K → $502K) through radical entitlement reform
- $22B infrastructure via hybrid financing: $5.5B GO bonds + $5.9B developer agreements + $10.6B Mello-Roos
2. A Picture of the Future
- SF current density vs. global cities: 6,800/km² today (London, Amsterdam) → 10,000/km² (NYC, Lyon, Montréal)
- What 2040 looks like: 22,600 new businesses, 181,000 jobs, 162 schools, $2,500 studio rents
- Unchanged neighborhoods: Sunset, Richmond, Noe Valley, Pacific Heights, the Haight
3. Where We Build: 30 Growth Zones
- Underbuilt transit corridors only: Mission, Geary, 19th Ave, India Basin, East SoMa, and 7 more
- Zone-by-zone unit targets, max heights, and delivery notes
- No changes to any low-density residential neighborhood
4. How We Build: Phased Delivery
- Four milestones: 17K (2030), 72K (2033), 166K (2037), 213K (2040)
- Fast-start zones first (India Basin, East SoMa); politically complex zones last (Ocean Beach, Wharf)
- Bond pause triggered if delivery falls >15% behind milestone
5. Entitlement Reform
- Impact fees: $101K → $15K. Inclusionary suspended — developers compensate nearby residents directly
- Prevailing wage and local hire waived for private construction; retained for public infrastructure
- Parking minimums eliminated. Flat $2K permit fee. 200 sq ft minimum unit size
- All exemptions expire at 213K units or Dec 31, 2042
6. Infrastructure & Financing
- $22B across 11 categories: schools ($7.9B), stormwater ($3.1B), water/sewer ($2.9B), power ($1.8B), and 7 more
- Two approaches: full $22B GO bond (7.1yr payback) vs. hybrid $5.5B GO bond (1.8yr payback)
- Infrastructure detail for all 11 line items
- Why direct payments are affordable housing: older buildings are naturally affordable; new BMR construction wastes hundreds of thousands per unit through layers of middlemen
7. How It Pays for Itself
- $3.1B/year recurring at build-out: property tax, sales tax, payroll tax, GRT, utilities
- $22.7B cumulative through 2040 vs. $22B infrastructure cost
- Every assumption sourced: SF Assessor, BTRC, BLS, DBI schedules, SFPUC rates
8. The Referendum
- Voter initiative locks in framework for 13 years — Board cannot repeal
- Discretionary review → ministerial. Project EIRs → programmatic EIR. Fragmented zoning → codified height/density
- Cannot fix: CEQA litigation, Coastal Commission (Ocean Beach), federal cleanup (Hunters Point)
- Full list of provisions, key terms, and what the measure does and does not do
9. Next Steps: Referendum Calendar
- Draft & file ballot language Mar-May 2026. Signature gathering Jun-Aug. Vote Nov 2026
- First bond tranche and Mello-Roos formation Q1 2027. Construction starts Jan 2028
- First housing delivered Q4 2029 in fast-track zones
10. Addendum: Full Referendum Text
- 9 sections of proposed ballot language: findings, financing, infrastructure, growth areas, permitting, entitlement reform, accountability, fiscal, effective date
- Ballot question names every entitlement suspension and the direct resident compensation requirement
- Subject to City Attorney review
11. Addressing the Opposition
- "Too expensive": $22.7B revenue vs $22B cost; hybrid needs only $5.5B voter approval
- "What about existing residents": developers pay neighbors directly — no fund, no nonprofits, no middlemen
- "Protecting a broken system": $1.1B/year in housing nonprofits with documented waste; this plan sends money to people, not institutions
1. Executive Summary
Over the last two decades, San Francisco has created extraordinary abundance. It has become the most important city in the world for the world's most important industry. The companies, products, and ideas that define modern life were built here. No other city on earth can claim that.
And yet San Francisco has lacked the ambition to grow alongside this creation. The city that invented the future has refused to build for it. Housing costs have spiraled. Teachers, nurses, firefighters, and the workers who keep the city running have been priced out. Families leave. The state has mandated 82,000 new homes by 2031, and the city is not on track.
San Francisco should inspire the world not only with its entrepreneurship, but with its quality of life. It should demonstrate that the city where the future is invented is also the city where the future is lived: a place that grows, that welcomes, that builds the schools and parks and transit that a great city requires, and that maintains its leadership as the global technology hub by being a place people actually want to live.
This is what that looks like.
The Plan
This proposal is a 13-year plan to build approximately 286,000 new homes across 30 designated growth zones, adding roughly 515,000 new residents to San Francisco by 2040. Infrastructure is funded by $22 billion through GO bonds ($5.5B), developer agreements ($5.9B), and Mello-Roos districts ($10.6B). Developers build and pay for everything on their own sites.
Radical entitlement reform within the growth zones cuts per-unit development cost from $989,000 to $502,000 — a 49% reduction. Impact fees drop from $101,069 to $15,000. Inclusionary mandates are suspended and replaced by a simple requirement: developers compensate existing residents near construction sites directly. No fund, no nonprofit intermediaries, no city administration. Prevailing wage, local hire, and parking minimums are suspended for private construction. All exemptions expire at 213,000 units or 2042. Public infrastructure retains all existing labor standards.
The math works. At full build-out, the new residents and businesses generate an estimated $3.1 billion per year in recurring tax revenue. Add one-time construction-phase revenues and cumulative revenue through 2040 reaches $22.7 billion against a $22 billion infrastructure cost. Under the hybrid financing approach, the GO bond pays back in 1.8 years.
Where, Not Everywhere
This is not a plan to turn quiet residential streets into construction zones. It is a plan to build on the underbuilt core arteries of the city: corridors that already have transit, commercial activity, and wide streets but are lined with single-story retail, surface parking lots, and underused industrial land.
The Mission has two BART stations and miles of corridor zoned for three stories. Geary Boulevard is the longest commercial street in San Francisco, served by the most-ridden bus line, and most of it is one story tall. 19th Avenue is a major arterial lined with gas stations and strip malls, slated for BRT. India Basin is largely vacant.
The Sunset, the Richmond, Noe Valley, Pacific Heights, the Haight, and every other low-density residential neighborhood are not part of this plan. Nothing in this proposal changes the character of those areas.
What 2040 Feels Like
A city of 1.34 million is a fundamentally different place. Density comparable to New York City, Lyon, and Montréal — still well below Barcelona or Paris. Every growth zone corridor transforms from single-story vacancy into walkable, active streetscape. Families stay. Commutes shorten. Housing costs fall because supply meets demand.
| Category | What Changes | Scale |
|---|---|---|
| Population | City grows from 828K to 1.34 million | +515,000 residents |
| Businesses | New restaurants, retail, services, clinics, gyms | ~22,600 new businesses |
| — Restaurants & cafés: Every corridor has street-level food and drink | ~3,400 new | |
| — Retail shops: Bookstores, groceries, pharmacies, boutiques | ~2,700 new | |
| Jobs | Neighborhood jobs within walking distance of home | ~181,000 new jobs |
| Schools | SFUSD reversal — new schools across all zones | 162 new schools |
| Transit | 38-Geary every 3 min at peak; new routes to India Basin, Southern Waterfront, Outer Mission | 8+ new routes |
| Parks | Maintain current 3.4 acres per 1,000 residents | ~1,300 new acres |
| Housing Cost | Studio on Geary: $2,500/mo instead of $4,500 | Supply meets demand |
| Unchanged | Sunset, Richmond, Noe Valley, Pacific Heights, the Haight | Same buildings, same character |
2. A Picture of the Future
SF Current Density
Density is often misunderstood. When people hear "denser city," they picture Hong Kong or Manhattan. But San Francisco is already a moderately dense city. The question is whether it should remain at a density that does not support enough housing for the people who want to live here.
| Today | Post-2040 | |
|---|---|---|
| Population | 828,000 | 1,343,070 |
| Land Area | 121 sq km (46.9 sq mi) | 121 sq km (46.9 sq mi) |
| Density (per sq km) | 6,843 | 11,100 |
| Density (per sq mi) | 17,723 | 28,635 |
Cities Like SF Today (~5,500-8,500 per sq km)
| City | Country | Population | Area (sq km) | Density (/km²) | Context |
|---|---|---|---|---|---|
| San Francisco | USA | 828,000 | 121 | 6,843 | REFERENCE - current density |
| London | UK | 8,800,000 | 1,572 | 5,598 | Dense core + residential neighborhoods |
| Madrid | Spain | 3,300,000 | 604 | 5,464 | Mid-rise European capital, transit-oriented |
| Mexico City | Mexico | 9,200,000 | 1,485 | 6,195 | Dense centro historico |
| Milan | Italy | 1,400,000 | 182 | 7,692 | Dense commercial center, comparable heights |
| Brussels | Belgium | 1,210,000 | 161 | 7,516 | EU capital with 6-8 story residential |
| Amsterdam | Netherlands | 905,000 | 219 | 4,132 | Canal-ring city; bikes + trams |
| Hong Kong | China (SAR) | 7,500,000 | 1,114 | 6,732 | Territory-wide avg masks ultra-dense core |
| Singapore | Singapore | 5,920,000 | 733 | 8,076 | High-rise city-state |
| Boston | USA | 675,000 | 125 | 5,400 | Closest US city by density to SF |
Cities Like SF Post-2040 (~8,000-12,000 per sq km)
At 10,012 per square kilometer, SF 2040 sits right alongside New York City, Lyon, and Montréal. Not Manhattan. NYC averaged across all five boroughs.
| City | Country | Population | Area (sq km) | Density (/km²) | Context |
|---|---|---|---|---|---|
| SF (2040) | USA | 1,343,070 | 121 | 11,100 | REFERENCE - post-build-out |
| Yokohama | Japan | 3,750,000 | 437 | 8,581 | Japan's 2nd city; mid-rise + transit |
| Taipei | Taiwan | 2,500,000 | 272 | 9,191 | Transit-rich, high-rise residential |
| Tel Aviv | Israel | 460,000 | 52 | 8,846 | Dense Mediterranean mid-rise core |
| New York City | USA | 8,300,000 | 783 | 10,600 | All five boroughs; close match to SF 2040 |
| Montréal | Canada | 1,760,000 | 166 | 10,602 | Walkable North American city, strong transit |
| Lyon | France | 515,000 | 48 | 10,729 | Dense 6-10 story Haussmann-style |
| Osaka | Japan | 2,750,000 | 225 | 12,222 | Transit-oriented high-rise + mid-rise |
| Buenos Aires | Argentina | 3,100,000 | 203 | 15,271 | European-style 8-12 story blocks |
| Barcelona | Spain | 1,640,000 | 101 | 16,238 | Famous dense grid; above SF 2040 range |
3. Where We Build: 30 Growth Zones
The plan identifies 30 growth zones. These are underbuilt commercial corridors, industrial areas, and transit-adjacent sites.
| ID | Area / District | Current Use | Max Height | Units | Pop. | Notes |
|---|---|---|---|---|---|---|
| 1 | Mission District | Mixed res./comm. | 8-15 stories | 30,000 | 54,000 | 2 BART stations, 24th/16th St corridors; constrained by parcel depth |
| 2 | Geary Corridor | Retail strips | 10-15 stories | 35,000 | 63,000 | ~65% parcel redevelopment at 10-15 stories; largest zone by corridor length |
| 3 | 19th Ave Corridor | Comm. + parking | 10-15 stories | 18,000 | 32,400 | GG Park to county line; gas stations, strip malls along future BRT |
| 4 | India Basin/Bayview | Indust. + vacant | 10-15 stories | 25,000 | 45,000 | Vacant land + shipyard; lowest cost, needs transit |
| 5 | East SoMa | Warehouses/tech | 25-35 stories | 25,200 | 45,360 | Remaining warehouse parcels |
| 6 | Mission Bay/Dogpatch | R&D/industrial | 20-30 stories | 15,300 | 27,540 | Only Dogpatch industrial sites remain |
| 7 | Mid-Market/Civic Ctr | Civic/lots/retail | 20-30 stories | 12,000 | 21,600 | Best transit; street conditions suppress demand |
| 8 | Ocean Beach/Gt Hwy | Coastal | 6-8 stories | 10,000 | 18,000 | 3.5 mi Great Hwy frontage; coastal cap |
| 9 | Southern Waterfront | Port/industrial | 20-25 stories | 12,750 | 22,950 | Brownfield cleanup + Port jurisdiction |
| 10 | Fisherman's Wharf | Tourist retail | 20-25 stories | 7,800 | 14,040 | Strongest political opposition of any zone |
| 11 | Caltrain Corridor | Railyards/parking | 8-12 stories | 10,000 | 18,000 | Low-risk transit-adjacent infill |
| 12 | Outer Mission/Excelsior | Comm. strip | 8-12 stories | 12,000 | 21,600 | Mission St south of Cesar Chavez; Balboa Park BART |
| TOTAL | 213,050 | 383,490 |
Table 1: Complete Build Plan. Population at 1.8 persons per unit.
Zone Profiles
Mission District — 30,000 units
The Mission is the plan's anchor. Two BART stations at 16th and 24th Streets already move tens of thousands of people daily, but the corridors above them are zoned for three stories. The Mission Street spine from Cesar Chavez to Duboce is lined with single-story retail, underused lots, and auto-oriented businesses on some of the most transit-rich land in the western United States. This zone targets the commercial corridors only — the residential side streets and Victorian blocks are not included. At 8-15 stories along the main arteries, 30,000 units is realistic given parcel depth constraints.
Geary Corridor — 35,000 units
Geary Boulevard is the longest commercial street in San Francisco and the route of the 38-Geary, the most-ridden bus line in the Muni system. From Masonic to the ocean, roughly four miles, the street is overwhelmingly one story tall: auto body shops, strip malls, fast food, and surface parking. This is the single most underbuilt corridor in the city relative to its transit capacity. At 10-15 stories on both sides of the boulevard, with the wide right-of-way already in place, 35,000 units reflects roughly 65% parcel redevelopment at 10-15 stories along both sides of the boulevard.
19th Avenue Corridor — 18,000 units
19th Avenue runs 2.5 miles from Golden Gate Park to the Daly City border, carrying Highway 1 traffic through what is essentially a suburban strip: gas stations, auto dealers, fast food, and the Parkmerced complex at the southern end. The corridor is slated for Bus Rapid Transit, which will transform the street into a true transit artery. The commercial frontage is only one lot deep on each side, which limits the buildable area. The Parkmerced master plan — already approved — anchors the southern end with a large-scale mixed-use redevelopment.
India Basin / Bayview — 25,000 units
India Basin and the surrounding Bayview-Hunters Point area contain the largest tracts of vacant and industrial land in San Francisco. The former Hunters Point Naval Shipyard is already undergoing remediation and redevelopment. Acquisition costs are the lowest in the city, displacement is minimal because most of the land is not residential, and the waterfront setting offers genuine amenity value. The primary constraint is transit: this area needs a new rail or BRT connection to downtown to support 25,000 units, which the infrastructure budget accounts for.
East SoMa — 25,200 units
East SoMa has already absorbed significant development over the past two decades, but pockets of warehouse and industrial parcels remain between 2nd and 6th Streets south of Harrison. These are large-footprint sites well-suited for 25-35 story towers. The area has excellent transit access — Caltrain, BART, Muni — and proximity to downtown. The zone is largely built out, and the 25,200-unit target reflects the remaining warehouse and industrial parcels.
Mission Bay / Dogpatch — 15,300 units
Mission Bay's residential phases are substantially complete. The remaining opportunity is in Dogpatch, where industrial sites along 3rd Street and the Caltrain right-of-way are converting to mixed-use. This is a proven development area with existing infrastructure, strong demand, and the T-Third Muni Metro line already in operation. The 15,300-unit target reflects the limited remaining acreage.
Mid-Market / Civic Center — 12,000 units
Mid-Market has the best transit access in the city: BART, Muni Metro, and multiple bus lines converge at Civic Center. It also has the most challenging street-level conditions — open drug markets, encampments, and vacant storefronts have suppressed residential demand for years. This zone will lag others until ground-floor conditions improve, but the transit fundamentals make it a long-term priority.
Ocean Beach / Great Highway — 10,000 units
The Great Highway runs 3.5 miles along the Pacific coast from Lincoln Way to Sloat Boulevard. The eastern side of the road has developable parcels, and the city's ongoing debate about converting the roadway creates an opportunity for a new coastal neighborhood. The 6-8 story height cap reflects coastal erosion risk and Coastal Commission requirements. Only east-side parcels are included; nothing is proposed on the beach or dune side.
Southern Waterfront — 12,750 units
The Southern Waterfront stretches from Pier 70 south through the former industrial parcels along Illinois Street and Cargo Way. Much of this land is controlled by the Port of San Francisco and requires brownfield remediation before residential use. The development timeline is longer than other zones due to environmental cleanup and Port Authority jurisdictional requirements, but the waterfront setting and proximity to Dogpatch make it a natural extension of the southeastern growth pattern.
Fisherman's Wharf / NE Waterfront — 7,800 units
Fisherman's Wharf will face the strongest political opposition of any zone. The tourism lobby and historic preservation advocates will fight significant change, and the 7,800-unit target reflects that constraint. The opportunity is in the underused parcels behind the tourist-facing waterfront — surface parking lots, one-story retail, and warehouse buildings along Bay Street and North Point that can support 20-25 story mixed-use development while preserving the waterfront character.
Caltrain Corridor — 10,000 units
Small parcels adjacent to the 22nd Street and Bayshore Caltrain stations, plus railyard-adjacent land, offer low-risk infill opportunities. These are transit-adjacent sites that require minimal infrastructure investment because the rail line already exists. Small parcel sizes limit the total to 10,000 units, but the political risk is also low — these are not neighborhood-character fights.
Outer Mission / Excelsior — 12,000 units
Mission Street continues as a neighborhood commercial corridor south of Cesar Chavez through the Outer Mission, Excelsior, and into Visitacion Valley. Balboa Park BART station anchors the middle of this strip. The character is similar to the upper Mission but at lower density — small retail, restaurants, and services serving a working-class residential area. At 8-12 stories along the commercial strip only, 12,000 units is proportional to the corridor's length and width, which is narrower than Geary or the main Mission spine.
4. How We Build: Phased Delivery 2027-2040
Construction is phased over 13 years with four milestones. Shovel-ready zones start first; zones requiring remediation or new transit ramp up later.
Phase 1: Foundation (2027-2030) — 16,800 units
The first three years focus on zones that can move immediately. Geary, 19th Avenue, and the Caltrain Corridor have large, simply-zoned commercial parcels with willing sellers, minimal residential displacement, and existing infrastructure. The Mission starts with corridor sites near BART. India Basin begins environmental prep work.
This phase proves the concept — first buildings go up, first residents move in, first revenue arrives. By 2030, 16,800 units are delivered and the city is earning $210 million per year in new recurring revenue. The programmatic EIR is complete and ministerial permitting is operational across all 12 zones.
Phase 2: Acceleration (2030-2033) — 55,400 additional units
The middle phase is where the plan hits its stride. The early zones are now proven markets with established demand, and developers scale up. Geary and Mission corridors are delivering at full pace. India Basin's transit connection is under construction, unlocking its first major residential phases. East SoMa and Mission Bay/Dogpatch fill in remaining warehouse sites with high-rise towers. Schools and parks from the first bond tranche are opening. By 2033, nearly 72,000 cumulative units are complete, recurring revenue crosses $944 million per year, and cumulative total revenue reaches $10.9 billion — already covering 39% of the infrastructure cost.
Phase 3: Build-out (2033-2037) — 93,600 additional units
This is the highest-volume phase. Every zone is active. The later-start areas — Southern Waterfront (brownfield cleanup complete), Fisherman's Wharf (political negotiation resolved), Mid-Market (street conditions improved by density itself) — are now delivering. Ocean Beach's Great Highway redevelopment is underway. The 19th Avenue BRT is operational, and the corridor is building out its full potential. By 2037, 172,000 cumulative units are in place, the population has grown by 299,000, and annual recurring revenue reaches $2.3 billion. The bonds are approaching payback. New schools, parks, and fire stations are operating across all 12 zones.
Phase 4: Completion (2037-2040) — 47,200 final units
The final phase completes the remaining units in every zone. The pace slows naturally as the easiest sites are built and the remaining parcels are smaller or more complex. Mid-Market and Fisherman's Wharf, the zones with the highest political friction, finish last. By 2040, all 213,050 units are delivered. San Francisco's population has grown to 1.21 million. Annual recurring tax revenue stands at $3.1 billion, cumulative revenue has reached $22.7 billion against $22 billion in infrastructure cost, and the city has added 162 new schools, 22 fire stations, and hundreds of acres of parks and open space.
| Zone | Total | 2030 Units | 2030 Pop | 2033 Units | 2033 Pop | 2037 Units | 2037 Pop | 2040 Units | 2040 Pop |
|---|---|---|---|---|---|---|---|---|---|
| Mission | 30,000 | 2,400 | 4,320 | 10,500 | 18,900 | 24,000 | 43,200 | 30,000 | 54,000 |
| Geary | 35,000 | 4,200 | 7,560 | 15,750 | 28,350 | 31,500 | 56,700 | 35,000 | 63,000 |
| 19th Ave | 18,000 | 2,700 | 4,860 | 9,000 | 16,200 | 17,100 | 30,780 | 18,000 | 32,400 |
| India Basin | 25,000 | 2,500 | 4,500 | 10,000 | 18,000 | 21,250 | 38,250 | 25,000 | 45,000 |
| East SoMa | 25,200 | 1,401 | 2,522 | 7,001 | 12,602 | 18,199 | 32,758 | 25,200 | 45,360 |
| Mission Bay | 15,300 | 540 | 972 | 3,600 | 6,480 | 9,901 | 17,822 | 15,300 | 27,540 |
| Mid-Market | 12,000 | 300 | 540 | 2,250 | 4,050 | 7,500 | 13,500 | 12,000 | 21,600 |
| Ocean Beach | 10,000 | 267 | 481 | 2,000 | 3,600 | 6,000 | 10,800 | 10,000 | 18,000 |
| S. Waterfront | 12,750 | 450 | 810 | 2,700 | 4,860 | 7,500 | 13,500 | 12,750 | 22,950 |
| Fisher. Wharf | 7,800 | 120 | 216 | 1,200 | 2,160 | 4,800 | 8,640 | 7,800 | 14,040 |
| Caltrain | 10,000 | 1,000 | 1,800 | 4,000 | 7,200 | 8,500 | 15,300 | 10,000 | 18,000 |
| Outer Mission | 12,000 | 960 | 1,728 | 4,200 | 7,560 | 9,600 | 17,280 | 12,000 | 21,600 |
| TOTAL | 213,050 | 16,838 | 30,309 | 72,201 | 129,962 | 165,850 | 298,530 | 213,050 | 383,490 |
| Milestone | 2030 (Yr 3) | 2033 (Yr 6) | 2037 (Yr 10) | 2040 (Final) |
|---|---|---|---|---|
| Cumulative Units | 20,188 | 89,686 | 206,730 | 286,150 |
| Cumulative Pop. | 36,338 | 161,435 | 372,114 | 515,070 |
| % Delivered | 7.9% | 33.9% | 77.8% | 100% |
5. Entitlement Reform: Cutting the Cost Per Unit in Half
Removing regulatory barriers without addressing cost barriers produces expensive housing faster. The average all-in development cost per unit in San Francisco today exceeds $900,000. Roughly half of that premium comes not from land or materials but from city-imposed requirements: impact fees, inclusionary mandates, prevailing wage rules, parking minimums, and design review processes that add months of carrying costs. These requirements apply uniformly across the city regardless of context, scale, or public benefit.
The referendum suspends all of them within the 12 growth zones for the duration of the build-out. This is not permanent deregulation — it is a project-specific exemption scoped to 213,000 units over 13 years, after which standard city requirements resume. The goal is to cut the per-unit cost low enough that middle-income households can afford the housing without subsidies.
Before and After: Per-Unit Development Cost
| Cost Component | Current SF | Growth Zone | Savings | Source |
|---|---|---|---|---|
| Hard Construction | $700,000 | $480,000 | $220,000 | Market-rate labor, no parking structure, design simplification |
| — Prevailing Wage | (included above) | (exempt) | ($84,000) | CA Labor Code — project exemption |
| — Parking (0.5 spaces) | (included above) | ($0) | ($60,000) | SF Planning Code §151 — waived |
| — Design Simplification | (included above) | (ministerial) | ($40,000) | No design review = simpler, faster |
| — Micro-Units Allowed | (included above) | (200sf min) | ($36,000) | Current 220sf min removed |
| Impact Fees | $101,069 | $15,000 | $86,069 | 2026 Fee Register — reduced to sewer + school only |
| Inclusionary (eff. cost) | $140,000 | $0 | $140,000 | SF Code §415 — replaced by direct program |
| Permits & Plan Check | $8,400 | $2,000 | $6,400 | DBI Fee Schedule — flat fee |
| Soft Costs / Carrying | $25,000 | $5,000 | $20,000 | Ministerial = fast close |
| Local Hire Compliance | $15,000 | $0 | $15,000 | SF Admin Code Ch. 83 — waived |
| TOTAL PER UNIT | $989,469 | $502,000 | $487,469 | 49% reduction |
What Each Reform Does
Impact Fee Reduction: $101,069 → $15,000
San Francisco's impact fees are the highest in the country. They fund schools, parks, transit, childcare, and affordable housing. For this project, the infrastructure bond directly funds schools, parks, transit, and fire/police — making most of the fees redundant. The $15,000 retained fee covers sewer connection and a minimal school assessment. Affordable housing funding is replaced by a direct program (see below).
Inclusionary Housing: 20% BMR → Direct Developer Payments
The current inclusionary ordinance requires 15-20.5% of units to be rented or sold below market rate. This is effectively a cross-subsidy — every market-rate buyer pays an additional ~$140,000 to cover the cost of the BMR units. The referendum suspends this requirement and replaces it with a single obligation: developers must compensate existing residents near their construction sites directly. No city fund, no nonprofit intermediaries, no administrative apparatus.
Prevailing Wage: Required → Exempt
Prevailing wage adds approximately 12-15% to construction labor costs in San Francisco, where market wages are already among the highest in the country. The exemption applies only to private residential construction in the 12 growth zones — not to the public infrastructure funded by the bond, which retains prevailing wage. This is the most politically difficult reform in the package. The building trades will oppose it. The tradeoff is ~$84,000 per unit in savings and tens of thousands of additional construction jobs that would not exist at the higher cost structure.
Parking Minimums: 0.5-1 space → 0
A structured parking space costs $60,000-$120,000 to build. Requiring parking in transit-served growth zones is a direct subsidy from non-car-owners to car-owners. Zero parking minimums do not mean zero parking — developers will build parking where the market demands it. They just won't be forced to build it where it isn't needed, particularly in zones with BART, Muni Metro, and BRT access.
Local Hire: 30% → Waived
The local hire mandate requires 30% of construction labor hours to be performed by San Francisco residents. At the scale of this project — 213,000 units over 13 years — there are not enough SF-resident construction workers to meet 30% of demand. The mandate creates compliance costs, limits the labor pool, and slows production. Waiving it for the growth zones allows the project to draw on the full Bay Area labor market.
6. Infrastructure & Financing: $22 Billion
The entitlement reform extends to public works. Streamlining public works permitting within the growth zones and competitive bidding without restrictive labor carve-outs reduces the infrastructure budget by 22% — from $28.3 billion to $22 billion. The same infrastructure gets built. It costs less.
| Category | Before | After | Rationale |
|---|---|---|---|
| K-12 Schools | $10.10B | $7.88B | ~162 new schools at ~$49M avg (was $62M) |
| Stormwater & Sea Level Rise | $4.00B | $3.12B | Combined sewer separation, waterfront barriers |
| Water & Sewer Trunk Lines | $3.75B | $2.93B | Expand mains to new zones |
| Power Grid Substations | $2.35B | $1.83B | PG&E capacity |
| Wastewater Treatment | $2.16B | $1.68B | SE + Oceanside plant upgrades |
| Parks & Open Space | $1.80B | $1.40B | Minimum parkland per resident |
| Road Resurfacing & Signals | $1.50B | $1.17B | No new highways |
| Fire Stations (22 new) | $1.08B | $0.84B | Coverage for new density zones |
| Bus Route Expansion | $0.72B | $0.56B | Muni frequency + new routes |
| Police Facilities | $0.58B | $0.45B | District stations + equipment |
| 911 / Emergency Dispatch | $0.22B | $0.17B | Call center + system capacity |
| TOTAL | $28.26B | $22.03B | 22% savings from reformed procurement |
Two Approaches to Financing
The $22 billion can be funded entirely through general obligation bonds, or through a hybrid structure that shifts most of the cost off the city's balance sheet. Both approaches deliver the same infrastructure on the same timeline. The difference is political: how large a bond measure voters need to approve.
Approach A: Full GO Bond — $22 Billion
The city issues $22 billion in general obligation bonds over 13 years, secured by property tax revenue. Simplest structure — one ballot measure, one funding source, one administrative framework. Requires a 2/3 supermajority vote, and $22 billion would be the largest municipal bond in American history. At $3.1 billion/year in recurring revenue, the bonds pay back in 7.1 years with a cumulative surplus of $0.7 billion through 2040.
Approach B: Hybrid Financing — $5.5 Billion GO Bond
| Source | Amount | Covers | Voter Approval? |
|---|---|---|---|
| GO Bonds | $5.5B | Wastewater treatment, stormwater/sea level rise, Muni expansion, 911 | Yes — 2/3 vote |
| Developer Agreements | $5.9B | Water/sewer trunk lines, power substations, road improvements | No |
| Mello-Roos / CFDs | $10.6B | Schools, parks, fire stations, police facilities | No |
| TOTAL | $22.0B | All infrastructure | $5.5B requires vote |
Developer Agreements are binding contracts where the developer builds zone-specific infrastructure — trunk sewer lines, power connections, road improvements — as a condition of approval. San Francisco already uses these for large projects: Parkmerced committed ~$1 billion. Scaling across 12 zones shifts $5.9 billion to the developers who benefit from it.
Mello-Roos / Community Facilities Districts are special tax districts where new residents pay an additional property tax assessment funding infrastructure bonds. This is how most large California developments have been financed for 40 years — Irvine, Sacramento, San Jose. San Francisco has barely used this tool. Mello-Roos districts in each growth zone fund schools, parks, fire stations, and police at $10.6 billion with zero city cash.
The hybrid approach reduces the voter-approved bond from $22 billion to $5.5 billion. At $3.1 billion/year in recurring city revenue, the $5.5 billion bond pays back in 1.8 years. Cumulative city revenue surplus through 2040 is $17.2 billion. The tradeoff: Mello-Roos assessments add approximately $200-$400/month to each new household's costs, partially offsetting the savings from entitlement reform.
Infrastructure Detail
K-12 Schools — $7.9 billion
Schools are the single largest line item because they are the single most important determinant of whether families stay in San Francisco. At $49 million average construction cost per school (prevailing wage exempt), the budget builds approximately 162 new schools across the 12 growth zones. SFUSD enrollment has been declining for over a decade. This reverses it.
Stormwater & Sea Level Rise — $3.1 billion
San Francisco's combined sewer system — which mixes stormwater and wastewater in a single pipe — cannot handle the additional volume from 213,000 new units without separation in the growth zones. This budget also covers waterfront barriers and pump stations for zones exposed to sea level rise, particularly India Basin, Mission Bay, and the Southern Waterfront.
Water & Sewer Trunk Lines — $2.9 billion
New trunk mains connecting growth zones to the city's water and sewer backbone. The existing system was sized for a city of 800,000. Expanding to 1.2 million requires new mains under the major corridors.
Power Grid Substations — $1.8 billion
PG&E's distribution grid does not have capacity for 213,000 new electrified units. New substations, feeder lines, and transformer capacity in each growth zone.
Wastewater Treatment — $1.7 billion
Upgrades to the Southeast Treatment Plant and Oceanside Water Pollution Control Plant to handle increased flow from 383,000 additional residents.
Parks & Open Space — $1.4 billion
San Francisco currently has approximately 3.4 acres of parkland per 1,000 residents. Maintaining that ratio for 383,000 new residents requires approximately 1,300 acres of new park space across the growth zones.
Road Resurfacing & Traffic Signals — $1.2 billion
No new highways. No new freeways. No road widening. This budget covers resurfacing of existing streets in and around the growth zones, new traffic signals, pedestrian improvements, and intersection redesigns for increased foot traffic.
Fire Stations — $840 million (22 new)
SFFD's response time standard is 4 minutes or less. Meeting that in 12 new density zones requires 22 new stations at approximately $27 million each, plus apparatus.
Bus Route Expansion — $560 million
New Muni routes serving India Basin, the Southern Waterfront, and the Outer Mission. Increased frequency on the 38-Geary, 19th Avenue BRT, and Caltrain corridor connections.
Police Facilities — $450 million
District stations and equipment to serve 12 new density zones. Staffing is operational budget, not capital.
911 / Emergency Dispatch — $170 million
Call center expansion and system upgrades to handle increased call volume from 383,000 additional residents.
Why Direct Payments Are Affordable Housing
Building new affordable housing makes no sense. New construction is the most expensive housing in any market — $600,000 to $1,000,000 per unit in San Francisco. Taking that unit and renting it at $1,200/month to one lottery winner requires a subsidy of $400,000-$700,000, routed through nonprofit developers, consultants, attorneys, and city agencies. The current system delivers a small number of expensive new units to a small number of people while consuming enormous public resources.
Older buildings are naturally affordable. A 40-year-old apartment with no construction debt, a locked Prop 13 tax base, and stabilized operating costs charges lower rent because the capital costs are already paid. This is how affordable housing works in every city in the world: people live in older buildings at lower rents. The filtering process — yesterday's luxury housing becomes today's middle-income housing and tomorrow's affordable housing — is the only mechanism that has ever produced affordable housing at scale.
Direct developer payments to nearby residents make existing older buildings more affordable while encouraging construction of new units. A renter in a 1970s building near the Geary Corridor paying $2,400/month who receives $300/month from the developer next door has an effective rent of $2,100 — affordable to a household earning $84,000. This reaches tens of thousands of households instead of the ~1,500 lottery winners per year the inclusionary system produces. And it eliminates every middleman, every nonprofit fee, every consultant, every compliance bureaucracy. Developer pays resident. That's it.
San Francisco spends over $1.1 billion per year on homelessness and housing nonprofits. The affordable housing pipeline produces roughly 1,000-1,500 units per year at average costs exceeding $700,000 per unit. Multiple Controller audits have documented waste, cost overruns, and lack of measurable outcomes. This plan eliminates every organization that profits from the housing shortage and replaces them with nothing. The developer writes checks to the neighbors. The money goes to people, not institutions.
7. How It Pays for Itself
All rates, fees, and formulas sourced from current SF tax code, the 2026 Impact Fee Register, and state law.
Property Tax Assumptions
| Parameter | Value | Source |
|---|---|---|
| Avg Assessed Value per Unit | $750,000 | Blended across zones (Prop 13 base) |
| Annual AV Increase | 2.0% | Prop 13 cap (CA Constitution Art XIIIA) |
| SF Property Tax Rate | 1.20% | SF Assessor: ~1.18-1.20% incl bonds |
| Resale Turnover Rate/yr | 5.0% | NAR avg for urban markets |
Transfer Tax Tiers (SF Business & Tax Code Art 12C)
| Tier | Rate | Detail |
|---|---|---|
| ≤$250K | 0.50% | $2.50 per $500 |
| $250K-$1M | 0.68% | $3.40 per $500 |
| $1M-$5M | 0.75% | $3.75 per $500 |
| $5M-$10M | 2.25% | $11.25 per $500 (Prop I) |
| Blended Residential | 0.68% | Most units sell in $250K-$1M range |
Development Impact Fees (per unit, reformed)
| Fee | Amount | Source |
|---|---|---|
| School Impact | $3,411 | CA Ed Code 17620: $3.79/gsf x 900 (state-mandated, cannot waive) |
| Sewer Connection | $11,589 | SFPUC connection fee (retained) |
| TOTAL PER UNIT | $15,000 | All other fees suspended per referendum Section 6 |
Standard SF impact fees total $101,069/unit. The referendum suspends $86,069/unit in fees within growth zones because the corresponding infrastructure (schools, parks, transit, childcare, affordable housing) is directly funded by the bond, developer agreements, and Mello-Roos districts. See Section 5 for full before/after breakdown.
Business & Consumer Tax Assumptions
| Parameter | Value | Source |
|---|---|---|
| People per Unit | 1.8 | New condo mix |
| Avg Consumer Spend/capita | $35,000 | BLS Consumer Expenditure, SF |
| SF Local Sales Tax Rate | 1.25% | Local share of 8.625% total |
| Businesses per 1,000 Residents | 59 | SF actual rate |
| Avg Gross Receipts/Business | $800,000 | SF small-mid avg |
| GRT Effective Rate | 0.30% | Prop M (2024) blended |
| Avg Jobs per New Business | 8 | Census SUSB avg for SF |
| Avg Annual Wage | $75,000 | BLS QCEW, service weighted |
| Payroll Expense Tax Rate | 0.60% | SF BTRC Sec 970 |
| Business Registration Fee | $2,500/yr | Prop M schedule |
| Utility Users Tax per Unit | $350/yr | 7.5% on ~$4,700 utility spend |
Construction-Phase Assumptions (reformed)
| Parameter | Value | Source |
|---|---|---|
| Avg Construction Cost/Unit | $480,000 | Reformed: no parking, prevailing wage exempt, design simplification |
| Permit Fee | $2,000 flat | Reformed: flat fee replaces 1.2% DBI schedule |
| Impact Fee/Unit | $15,000 | Reformed: sewer + school only (was $101,069) |
| Materials Sales Tax | 1.25% | Local share on ~40% of hard cost |
| Construction GRT | 0.20% | Prop M Category 3 |
| Construction Payroll Tax/Unit | $1,728 | ~60% labor x 0.6% rate (lower base) |
Revenue Projections by Milestone
| Revenue Stream | 2030 (Yr 3) 16,838 units | 2033 (Yr 6) 72,201 units | 2037 (Yr 10) 165,850 units | 2040 (Yr 13) 213,050 units | Source |
|---|---|---|---|---|---|
| Annual Recurring | |||||
| Property Tax | $161M | $732M | $1,821M | $2,481M | AV x Prop 13 growth x 1.2% |
| Transfer Tax (resales) | $4.6M | $20.8M | $51.6M | $70.3M | 5% turnover x value x 0.68% |
| Sales Tax | $13.3M | $56.9M | $130.6M | $167.8M | Units x 1.8 x $35K x 1.25% |
| Gross Receipts Tax | $4.3M | $18.4M | $42.3M | $54.3M | Prop M blended rates |
| Commercial Property Tax | $10.3M | $44.2M | $101.5M | $130.3M | New commercial AV x 1.2% |
| Payroll Tax | $6.5M | $27.6M | $63.4M | $81.5M | New jobs x wage x 0.6% |
| Business Registration | $4.5M | $19.2M | $44.0M | $56.5M | Prop M schedule |
| Utility Users Tax | $5.9M | $25.3M | $58.0M | $74.6M | 7.5% on utility bills |
| TOTAL RECURRING/YR | $210M | $944M | $2,311M | $3,116M | |
| One-Time (period) | |||||
| Impact Fees | $253M | $830M | $1,405M | $708M | All planning + utility fees |
| Transfer Tax (initial) | $91M | $318M | $582M | $311M | First sale x 0.68% |
| Building Permits | $34M | $111M | $187M | $94M | DBI 1.2% of valuation |
| Construction Materials | $40M | $133M | $225M | $113M | 1.25% on 40% of hard cost |
| Construction GRT | $16M | $53M | $90M | $45M | Prop M Category 3 |
| Construction Payroll | $29M | $96M | $162M | $82M | Labor cost x 0.6% |
| TOTAL ONE-TIME | $463M | $1,541M | $2,651M | $1,354M | |
| 2030 | 2033 | 2037 | 2040 | |
|---|---|---|---|---|
| Annual Recurring | $0.21B | $0.94B | $2.31B | $3.12B |
| Cumulative One-Time | $0.5B | $2.0B | $4.7B | $6.0B |
| Cumulative Total Revenue | $0.8B | $4.0B | $13.2B | $22.7B |
Data Sources
- SF Citywide Development Impact Fee Register (eff Jan 1, 2026) - sfplanning.org
- SF Business & Tax Regulations Code Art 12C - Transfer Tax tiers
- Prop M (Nov 2024) - GRT restructuring, 7 categories, $5M threshold
- SF Controller FY25-26/26-27 Revenue Letter
- SFPUC Rate Schedules (eff 7/1/2025)
- CA Education Code 17620
- DBI Development Impact Fee Collection Unit
8. The Referendum
Why a Referendum
San Francisco's housing crisis is fundamentally a regulatory crisis. The city has the land, the demand, and the capital. What it lacks is a system that allows housing to be built at the speed and scale the market would otherwise support. A voter-approved initiative is the strongest possible vehicle for fixing this because it creates law that the Board of Supervisors cannot undo without another public vote. Ordinances passed by the Board can be repealed by the Board. A referendum cannot.
This matters because the political dynamics that created the housing shortage are still in place. The Board has repeatedly downzoned land, added discretionary review layers, and expanded opportunities for project opponents to delay or kill housing. A referendum locks in the regulatory framework for 13 years and removes the ability of future Boards to backslide.
What the Referendum Fixes
Discretionary Review → Ministerial Approval
The single biggest obstacle to housing in San Francisco is discretionary review. Every project, no matter how code-compliant, goes through a multi-year approval process where neighbors, the Planning Commission, and the Board of Supervisors can block, shrink, or delay it. A single appeal can add 18 months. This referendum mandates ministerial (by-right) approval for any project in the 12 growth zones that meets the building code and the height/density limits established by the plan. If it's code-compliant, it gets a permit. No hearings, no appeals, no commission votes. SB 35, signed into state law in 2017, already established the legal precedent that ministerial approval for housing is constitutional in California.
Project-by-Project EIR → Programmatic EIR
Under current practice, every significant housing project requires its own Environmental Impact Report under CEQA — a process that takes 18-36 months and costs $1-5 million per project. This referendum funds and mandates a single Programmatic EIR covering all 12 growth zones, completed within 18 months of the effective date. Individual projects that fall within the scope of the programmatic EIR do not need separate environmental review. Multiple California cities have used programmatic EIRs successfully, including the Downtown Plan EIR that San Francisco itself adopted in 2023. This is proven, legally tested, and the single most effective way to collapse the permitting timeline from years to months.
Infrastructure Chicken-and-Egg → Pre-Funded Backbone
Developers will not build where there is no sewer capacity, and the city will not build sewer capacity until developers commit. This deadlock has stalled growth in every potential expansion area for decades. The $22 billion infrastructure financing — GO bonds for citywide systems, developer agreements for zone-specific connections, Mello-Roos for schools and parks — breaks the deadlock by pre-funding all backbone infrastructure so that developers can build with confidence that the public systems will be in place when residents arrive.
Fragmented Zoning → Codified Height and Density
San Francisco's current zoning is a patchwork of overlapping districts, special use districts, and design guidelines that make it nearly impossible for a developer to know what they can build on a given parcel without months of pre-application review. The referendum establishes clear, codified height and density limits for each of the 12 zones. A developer can look at a parcel, check the zone map, and know exactly what is allowed. This certainty is itself a form of infrastructure — it reduces the cost and risk of development, which translates directly into lower housing costs.
What the Referendum Cannot Fix
CEQA Litigation
A programmatic EIR reduces exposure but does not eliminate it. Project opponents can still file CEQA lawsuits on project-specific grounds — inadequate traffic analysis, shadow impacts, historic resources, or claims that a project falls outside the scope of the programmatic EIR. Each lawsuit adds 1-2 years even if it ultimately fails. At this scale, expect dozens of lawsuits across the 12 zones. The plan accounts for this by building legal defense costs into the infrastructure budget and by setting delivery milestones that assume some litigation delay. But no local ballot measure can reform CEQA itself — that requires state legislation.
Coastal Commission Jurisdiction
The Ocean Beach / Great Highway zone falls under California Coastal Commission jurisdiction. A local ballot measure cannot override state coastal authority. The 10,000 units proposed for that zone require Coastal Commission approval through a Local Coastal Program amendment, which is a separate multi-year process with its own environmental review and public hearings. This zone is the most legally fragile in the plan and the most likely to underdeliver or experience significant delays.
Federal Jurisdiction at Hunters Point
Portions of the India Basin / Bayview zone include the former Hunters Point Naval Shipyard, a federal Superfund site. Remediation timelines are controlled by the U.S. Navy and the EPA, not the city. A local ballot measure cannot accelerate federal environmental cleanup. The delivery schedule for that zone assumes remediation proceeds on the current federal timeline, but delays are possible and outside the city's control.
What It Does
- Authorizes $22B in infrastructure: $5.5B GO bonds, $5.9B developer agreements, $10.6B Mello-Roos districts
- Mandates ministerial (by-right) approval for code-compliant projects in all 12 growth zones
- Funds a single Programmatic EIR covering all 12 zones, eliminating project-by-project environmental review
- Codifies height and density limits that cannot be reduced by future Boards without a public vote
- Suspends inclusionary housing mandates; developers compensate nearby residents directly — no fund, no nonprofits, no city administration
- Reduces impact fees from $101,069 to $15,000 per unit (sewer + school only); other infrastructure funded by bond
- Exempts private residential construction in growth zones from prevailing wage and local hire requirements
- Eliminates parking minimums in growth zones
- Flat $2,000 permit fee replaces percentage-based fee schedule
- All exemptions are project-specific and expire at completion of 213,000 units or December 31, 2042
- Public infrastructure retains prevailing wage and local hire
- Controller audits bond spending annually. Requires 2/3 voter approval (66.67%)
Key Provisions
Financing: $22B total. GO bonds ($5.5B) for citywide systems. Developer agreements ($5.9B) for zone-specific trunk lines and power. Mello-Roos ($10.6B) for schools, parks, fire, police.
Infrastructure: $7.9B schools, $3.1B stormwater, $2.9B water/sewer, $1.8B power, $1.7B wastewater, $1.4B parks, $1.2B roads, $0.8B fire, $0.6B bus, $0.5B police, $0.2B 911.
Zones: 12 zones with codified height/density limits. Board can reallocate up to 10% between zones by supermajority.
Milestones: 2030: 17K. 2033: 72K. 2037: 166K. 2040: 213K. Miss by >15% triggers bond pause.
Permitting: Ministerial approval for code-compliant projects. Programmatic EIR covers all 12 zones. Flat $2,000 permit fee.
Entitlement Reform: Impact fees reduced to $15K/unit. Inclusionary suspended — developers compensate nearby residents directly. Prevailing wage and local hire waived for private construction. Parking minimums eliminated. All exemptions expire at 213K units or Dec 31, 2042.
Revenue: $3.1B/yr recurring at build-out. $6B one-time through 2040. $22.7B cumulative.
Affordability: Inclusionary mandates replaced by direct developer payments to existing residents near construction. No city fund, no nonprofits, no intermediaries. Older buildings are naturally affordable — direct payments make them more so.
Labor: Private residential construction: market-rate wages. Public infrastructure: prevailing wage and 30% local hire retained.
Legal: GO bonds = 2/3 vote. Prop 13/218 compliant. Voter initiative — cannot be repealed by Board.
9. Next Steps: Referendum Calendar
Phase 1: Draft & File (March-May 2026)
| Date | Action |
|---|---|
| Mar-Apr 2026 | Draft ballot language, circulate to Board/Mayor/SFUSD/SFPUC/unions/housing orgs |
| May 2026 | Controller fiscal analysis, City Attorney legal review |
| May 30, 2026 | File ballot title & summary with City Attorney |
Phase 2: Signature Gathering (June-August 2026)
| Date | Action |
|---|---|
| Jun 1 | Dept of Elections certifies petition |
| Jun-Jul | Collect ~90K signatures (67K valid needed) |
| Aug 1 | Submit petitions |
| Aug 31 | Verification complete, measure certified for November ballot |
Phase 3: Campaign & Vote (Sep-Nov 2026)
| Date | Action |
|---|---|
| Sep | Controller impartial analysis published, voter guide arguments filed |
| Sep-Oct | Campaign: town halls in 12 zones, labor + housing + business coalition |
| Nov 3 | Election Day - needs 66.67% supermajority |
Phase 4: Build (Q1 2027 onward)
| Date | Action |
|---|---|
| Q1 2027 | First GO bond tranche sold ($2-3B), Mello-Roos districts formed, first developer agreements executed |
| Q2 2027 | First infrastructure RFPs |
| Jan 2028 | Construction starts |
| Q4 2029 | First housing units delivered (fast-track zones) |
Immediate Next Steps
- Controller models debt service + property tax rate impact
- City Attorney reviews draft for legal sufficiency
- Decide: full GO bond ($22B, 2/3 vote) vs. hybrid ($5.5B GO + developer agreements + Mello-Roos)
- Build coalition: SPUR, YIMBY Action, Housing Action Coalition, building trades, SFUSD, SFPUC
- Draft full referendum text (see addendum)
- Finalize developer fee approach
10. Addendum: Full Text of Proposed Referendum
Full text of proposed ballot measure. Subject to City Attorney review and certification.
BALLOT TITLE AND SUMMARY
Shall the City and County of San Francisco finance $22 billion in public infrastructure through general obligation bonds, developer agreements, and community facilities districts; suspend inclusionary mandates, prevailing wage, local hire, and parking minimums for private residential construction in 12 designated growth zones; reduce impact fees to $15,000 per unit; require developers to compensate existing residents near construction sites; mandate ministerial permitting; and fund a programmatic environmental impact report — all to support approximately 213,000 new homes, with all spending subject to independent audit and citizen oversight?
Requires 2/3 (66.67%) approval.
SECTION 1. FINDINGS
(a) San Francisco faces a severe housing crisis. The median home price exceeds $1.3 million.
(b) California has mandated 82,000 new homes by 2031. The City is not on track.
(c) Root cause: insufficient infrastructure + 4-year permitting process + per-unit cost structure that prevents middle-income housing production.
(d) Cities worldwide support higher densities with high quality of life.
(e) The all-in development cost per housing unit in San Francisco exceeds $900,000. Approximately half of this premium results from city-imposed requirements that can be suspended without compromising health or safety.
(f) New construction is inherently the most expensive housing in any market. Older existing buildings with paid-off mortgages and stabilized operating costs are naturally more affordable. Direct financial assistance to residents of existing buildings provides affordable housing more efficiently, to more people, than building new units at $600,000-$1,000,000 each and renting them below cost to a small number of lottery winners.
(g) The City currently spends over $1.1 billion per year on homelessness and housing-related nonprofits. Multiple Controller and Budget & Legislative Analyst audits have documented waste, cost overruns, and lack of measurable outcomes in this spending.
(h) 213,000 new homes generate $3.1B/yr recurring plus $6B one-time through 2040, totaling $22.7B.
(i) San Francisco's economy depends on the people who live here.
SECTION 2. FINANCING
(a) Authorize up to $5.5B in general obligation bonds for citywide infrastructure (wastewater, stormwater, transit, emergency services).
(b) Authorize formation of Community Facilities Districts (Mello-Roos) in each designated growth area to fund schools, parks, fire stations, and police facilities, not to exceed $10.6B in aggregate.
(c) Require development agreements for zone-specific infrastructure (water/sewer trunk lines, power substations, road improvements) as a condition of ministerial permit issuance, not to exceed $5.9B in aggregate.
(d) GO bonds issued in tranches; no single tranche >$2B without Board vote.
(e) Restricted fund for capital construction only. (f) Tax rate capped at debt service level. Not a new tax.
SECTION 3. INFRASTRUCTURE
(a) Schools: $7.88B. (b) Stormwater/sea level rise: $3.12B. (c) Water/sewer trunk lines: $2.93B. (d) Power grid: $1.83B. (e) Wastewater treatment: $1.68B. (f) Parks/open space: $1.40B. (g) Road resurfacing/signals: $1.17B. (h) Fire stations: $0.84B. (i) Bus route expansion: $0.56B. (j) Police facilities: $0.45B. (k) 911/emergency dispatch: $0.17B.
Board may reallocate up to 10% between categories with 30-day notice. Total cannot exceed $22B.
SECTION 4. DESIGNATED GROWTH AREAS
Mission District: 30,000. Geary Boulevard: 35,000. 19th Ave Corridor: 18,000. India Basin/Bayview: 25,000. East SoMa: 25,200. Mission Bay/Dogpatch: 15,300. Ocean Beach/Great Highway: 10,000. Mid-Market: 12,000. Southern Waterfront: 12,750. Caltrain Corridor: 10,000. Fisherman's Wharf: 7,800. Outer Mission/Excelsior: 12,000.
Boundaries follow existing zoning districts.
SECTION 5. STREAMLINED PERMITTING
(a) Ministerial approval; 90-day decision. No discretionary review.
(b) Single Programmatic EIR covering all 12 zones within 18 months.
(c) Building Code, fire safety, ADA compliance still required.
(d) Flat permit fee of $2,000 per unit replaces percentage-based fee schedule.
SECTION 6. ENTITLEMENT REFORM — GROWTH ZONE EXEMPTIONS
(a) Impact fees within designated growth areas are reduced to $15,000 per unit, covering sewer connection and school assessment only. All other infrastructure is funded by the financing authorized in Section 2.
(b) Inclusionary housing mandates under Planning Code Section 415 are suspended within designated growth areas for the duration of this measure. As a condition of ministerial permit issuance, developers shall compensate existing residents near construction sites directly. Amount, method, and duration of compensation are at the developer's discretion. No city fund, nonprofit intermediary, or administrative program is created by this section.
(c) Prevailing wage requirements under California Labor Code are waived for private residential construction within designated growth areas. Public infrastructure funded under Section 2 retains prevailing wage.
(d) Local hire requirements under Administrative Code Chapter 83 are waived for private residential construction within designated growth areas. Public infrastructure funded under Section 2 retains 30% local hire.
(e) Minimum parking requirements under Planning Code Section 151 are eliminated within designated growth areas. Developers may build parking at their discretion.
(f) Minimum unit size within designated growth areas is reduced to 200 square feet.
(g) All exemptions in this section apply only to private residential construction within designated growth areas and expire upon issuance of permits for 213,000 cumulative units or December 31, 2042, whichever comes first. Upon expiration, standard city requirements resume.
SECTION 7. ACCOUNTABILITY AND OVERSIGHT
(a) Citizens' GO Bond Oversight Committee reviews spending.
(b) Controller conducts independent annual audit.
(c) Milestones: 2030 ~17K, 2033 ~72K, 2037 ~166K, 2040 ~213K.
(d) If permits fall >25% below milestone, Board hearing within 60 days before additional tranches.
SECTION 8. FISCAL PROVISIONS
(a) Estimated GO bond repayment: ~$13B over bond life (principal + interest on $5.5B).
(b) Mello-Roos assessments repaid by new residents over 25-30 years.
(c) At full build-out: $3.1B/yr recurring city revenue.
(d) Combined GO bond tax rate will not exceed $0.05 per $100 AV above current rate.
SECTION 9. EFFECTIVE DATE, DURATION, SEVERABILITY
(a) Effective January 1, 2027 or 10 days after vote declaration.
(b) GO bond authority expires December 31, 2042. Mello-Roos districts continue per their formation documents.
(c) Severability.
(d) Board may amend by 2/3 vote but cannot increase total financing, reduce growth zone boundaries, or reimpose suspended entitlement requirements without voter approval.
11. Addressing the Opposition
"It's Too Expensive"
The infrastructure costs $22 billion. Cumulative tax revenue through 2040 totals $22.7 billion. Under the hybrid financing approach, only $5.5 billion requires voter-approved GO bonds — the rest is funded by developers and new residents. Property tax alone from 213,000 new units generates over $2.4 billion per year, every year, permanently. The cost of doing nothing is losing $3.1 billion per year in revenue the city will never collect.
"What About Existing Residents?"
The old approach required 15-20% of new units to be rented below market rate. This added ~$140,000 to every market-rate unit, produced expensive new apartments for a small number of lottery winners, and funneled hundreds of millions through nonprofit developers, consultants, and city agencies. The fundamental premise — that the way to provide affordable housing is to build brand-new units and sell them at a loss — is wrong.
New construction is the most expensive housing in any market. An older building with its mortgage paid off, its Prop 13 base locked in, and its operating costs stabilized is naturally affordable. That is how affordability works in every city in the world: people live in older buildings at lower rents. The inclusionary system fights this reality by spending $600,000-$1,000,000 to build a new unit and then renting it for $1,200/month to one household. The subsidy per household is staggering. The number of people served is tiny. And the money passes through layers of organizations that take their cut before it reaches anyone.
This plan does the opposite. Developers compensate existing residents near their construction sites directly. A renter paying $2,400/month who receives $300/month from the developer next door has an effective rent of $2,100 — affordable to a household earning $84,000. No fund, no nonprofit, no consultant, no compliance report. Developer pays resident. Every dollar goes to the person.
Why This Is Better
- Tens of thousands of households benefit instead of ~1,500 lottery winners per year under the old system.
- Older buildings become the affordable housing. Direct payments reduce effective rents in existing stock — which is where affordable housing actually exists, not in expensive new construction.
- Zero middlemen. No fund, no nonprofits, no consultants, no city administration. Developer to resident.
- It changes the politics. A new building going up next door means a check in the mail. Existing residents become allies of construction instead of opponents.
- Lower market rents for everyone. Removing the $140K/unit cross-subsidy means new units rent at $2,500 instead of $4,500. More supply at lower prices benefits the entire market.
- It eliminates the corruption. San Francisco spends $1.1 billion/year on homelessness and housing nonprofits. Multiple Controller audits have found waste, cost overruns, and lack of outcomes. This plan routes money directly to people and eliminates every organization that profits from the housing shortage.
The Real Opposition: Protecting a Broken System
The loudest opposition comes from organizations that have built careers and budgets around keeping the city small. The housing shortage is not an accident. It is a business model.
San Francisco spends over $1.1 billion per year on homelessness and housing-related nonprofits. The problem has not improved. The incentive structure rewards managing the crisis, not ending it.
Multiple audits by the Controller and Budget & Legislative Analyst have found widespread waste, lack of accountability, and in some cases fraud in nonprofit contracting. Organizations receive tens of millions in annual city contracts with minimal performance requirements. Their political influence blocks housing development, which would reduce the crisis that justifies their funding.
Paying for It by Cutting Waste
- $1.1B/year on homelessness nonprofits. A 10% efficiency gain frees $110M/year.
- Controller has identified hundreds of millions in contracts with inadequate performance measurement.
- Multiple nonprofits charge 30-40% administrative overhead.
- Direct resident benefit at $1K/household/year for 95K households costs $95M/year — easily covered.
The opposition wants to keep San Francisco small because a small city with a housing shortage is profitable for the organizations that claim to be solving the problem. This plan builds the housing, generates the revenue, and shares the benefits directly with residents. The math works. The only people who lose are the ones who have been profiting from the status quo.
About
I'm Brad. I work in tech and I've lived in San Francisco for 14 years. I want the city to grow, but in a way that benefits new residents and old.
SF2040 started with the idea that the only way to fix San Francisco real estate is to fix everything at once in one giant referendum. Without this, we'll be stuck fighting over every building and street in the city, one by one, to no one's benefit.
The bill must please all major coalitions in the city, while also angering all of them a little. Everyone wins and everyone compromises a little. That's the only path forward.
If this excites you, please sign up here.